Management of production

Production Orders describe the operations that need to be carried out and the raw materials usage for each stage of production, You use specifications (bills of materials) to work out the raw material requirements and the manufacturing orders needed for the finished products.

Manufacturing has the following results:

  • Stock reduction: consumption of raw materials,

  • Stock increase: production of finished goods,

  • Analytic costs: manufacturing operations,

  • Added accounting value of stock: by the creation of value following the transformation of products.

物料清单

Use of Bills of Materials

Bills of Materials are documents that describe the list of raw materials used to make a finished product. To illustrate the concept of specification you're going to work on a cabinet where the manufacturing plan is given by the figure Plan of construction of a cabinet.

/doc_static/5.0/_images/mrp_armoire.png

Plan of construction of a cabinet

The cabinet is assembled from raw materials and intermediate assemblies:

Product Definitions before defining Bills of Materials

Product Code

描述

ARM100

Cabinet

PANLAT

Wooden Side Panel

PANA100

Rear Panel

PROFIL

Metal Strut

ETA100

Shelf

PLET100

Shelf Panel

BOIS002

Wood Panel

BOIS010

Wood Panel

TAQ000

Panel Pins

LIN040

Lintel

To describe how to assemble this cabinet, you define a bill of materials for each intermediate product and for the final cabinet assembly. These are given by the table below.

Bill of Materials for 1 ARM100 Unit

Product Code

Quantity

Unit of Measure

PANLAT

2

Unit

PANA100

1

Unit

PROFIL

4

Unit

ETA100

3

Unit

Bill of Materials for 1 ETA100 Unit

Product Code

Quantity

Unit of Measure

PLET100

1

Unit

TAQ000

4

Unit

Bill of Materials for 1 PLET100 Unit

Product Code

Quantity

Unit of Measure

BOIS010

0.083

m2

Bill of Materials for 1 PROFIL Unit

Product Code

Quantity

Unit of Measure

LIN40

0.25

m

Bill of Materials for 1 PANA100 Unit

Product Code

Quantity

Unit of Measure

BOIS002

0.25

m2

Bill of Materials for 1 PANLAT Unit

Product Code

Quantity

Unit of Measure

BOIS002

0.083

m2

The bills of materials are then used by the software to calculate the raw material needs based on the requirements of the finished products. Then if you want to manufacture 10 cabinets, the system can calculate what will be consumed:

Total Quantities

Product Code

Quantity

Unit of Measure

BOIS002

2 * 0.083 + 0.25

m2

LIN040

1

m

BOIS002

0.083 * 3

m2

TAQ000

12

Unit

小技巧

物料清单

To see the bill of materials in tree view, use the menu Manufacturing ‣ Configuration ‣ Bill of Materials ‣ Bill of Materials Structure.

/doc_static/5.0/_images/mrp_bom_tree.png

Bill of Materials structure

Use the menu Manufacturing ‣ Configuration ‣ Bill of Materials ‣ New Bill of Materials to define a new bill of materials.

/doc_static/5.0/_images/mrp_bom.png

Screen defining a Bill of Materials

In the area below the bill of materials you should set the finished product, which will be manufactured or assembled. Once the product has been selected, OpenERP automatically completes the name of the bill of materials and the default Unit of Measure for this product.

The type of BoM (BoM Type : Phantom or Normal) and the Routing field will be described in more detail later in the chapter.

After this you can select the raw materials that are used in the manufacture of the finished product. The quantities are set out in a report based on the quantities of finished product and the quantities needed to produce them from the bill of materials.

The second tab, Revisions, is used to set down all the changes made to the bill of materials. After each change you can specify a revision number and some notes on the modifications you carried out.

注解

Simplified View

The Revisions tab is only visible if the user works in the Extended View mode (which means that the user must belong to the group Usability / Extended View .

/doc_static/5.0/_images/mrp_bom_revision.png

Revisions of a Bill of Materials

In the third tab, Properties, you can put a free text reference to a plan, a sequence number that is used to determine the priorities between bills of materials, dates between which a bill of materials is valid, and values for rounding and product efficiency.

Rounding is used to set the smallest Unit of Measure for expressing the quantities of the selected product. So if you set the rounding to 1.00 you'll not be able to manufacture half a piece. The Efficiency of the product lets you indicate the percentage you lose during manufacture. This loss can be set for the finished product or for each raw materials line. The impact of this efficiency figure is to reserve more raw materials for manufacture than you'd otherwise use just from the Bill of Materials calculations.

The final part of the third tab lets you set some properties for the product's manufacturing processes. These will be detailed further on in the chapter in the section on configurable products.

多层次BOM

In OpenERP each line of a bill of materials may itself be a bill of materials. So you can define BoMs with several levels. Instead of defining several BoMs for the cabinet in the figure Plan of construction of a cabinet you could define the single bill of materials below:

Single Bill of Materials for 1 ARM100 Unit

Product Code

Quantity

Unit of Measure

ARM100

1

Unit

PANLAT

2

Unit

BOIS002

0.166

m2

PANA100

1

Unit

BOIS002

0.25

m2

PROFIL

4

Unit

LIN040

1

m

ETA100

3

Unit

PLET100

3

Unit

BOIS010

0.249

m2

TAQ000

12

Unit

OpenERP behaves differently depending on whether the bill of materials is defined in several small BoMs each on a single level or in one BoM tree-structured on several levels.

So if you select a BoM using intermediate products that automatically generates production orders based on calculated requirements, OpenERP will propose manufacturing an intermediate product. To manufacture a cabinet, you'd create 6 production orders:

Production Order

Product Code

Quantity

Unit of Measure

PLET100

3

Unit

BOIS010

0.25

m2

Production Order

Product Code

Quantity

Unit of Measure

ETA100

3

Unit

PLET100

3

Unit

TAQ000

12

Unit

Production Order

Product Code

Quantity

Unit of Measure

PROFIL

4

Unit

LIN040

1

m

Production Order

Product Code

Quantity

Unit of Measure

PANA100

1

Unit

BOIS002

0.25

m2

Production Order

Product Code

Quantity

Unit of Measure

PANA100

2

Unit

BOIS002

0.17

m2

Production Order

Product Code

Quantity

Unit of Measure

ARM100

1

Unit

PANLAT

2

Unit

PANA100

1

Unit

PROFIL

4

Unit

ETA100

3

Unit

In the case where a single bill of materials is defined in multiple levels, a single manufacturing order will be generated for each cabinet, including all of the sub-BoMs. You'd then get the following production order:

Single manufacture from a tree-structured BoM

Product Code

Quantity

Unit of Measure

ARM100

1

Unit

BOIS002

0.17

m2

BOIS002

0.25

m2

LIN040

1

m

BOIS010

0.25

m2

TAQ000

12

Unit

虚拟件BOM

If a finished product is defined using intermediate products that are themselves defined using other BoMs, OpenERP will then propose the manufacture of each intermediate product. This will give several production orders. If you only want a single production order you can define a single BoM with several levels.

Sometimes, however, it is useful to define the intermediate product separately and not as part of a multi-level assembly even if you don't want separate production orders for intermediate products.

In the example, the intermediate product ETA100 is used in the manufacture of several different cabinets. So you'd want to define a unique BoM for it even if you didn't want any instances of this product to be built, nor wanted to re-write these elements in a series of different multi-level BoMs.

If you only want a single production order for the complete cabinet, and not one for the BoM itself, you can define the BoM line corresponding to product ETA100 in the cabinet's BoM as type Phantom. Then it will automatically put ETA100's BoM contents into the cabinet's production order even though it's been defined as multi-level.

This way of representing the assembly is very useful because it allows you to define reusable elements of the assembly and keep them isolated.

If you define the BoM for the ARM100 cabinet in the way shown by the table below, you'll get two production orders when the order is confirmed, as shown in the tables below that.

Definition and use of phantom BoMs

Product Code

Quantity

Unit of Measure

Type of BoM

ARM100

1

Unit

normal

PANLAT

2

Unit

normal

PANA100

1

Unit

phantom

PROFIL

4

Unit

phantom

ETA100

3

Unit

phantom

Production Order from phantom BoMs

Product Code

Quantity

Unit of Measure

ARM100

1

Unit

PANLAT

2

Unit

BOIS002

0.25

m2

LIN040

1

m

BOIS010

0.25

m2

TAQ000

12

Unit

Production Order from normal BoM

Product Code

Quantity

Unit of Measure

PANLAT

2

Unit

BOIS002

0.17

m2

Assembly Bills of Materials

注解

Sales Bills of Materials

In some software this is named a Sales Bill of Materials. In OpenERP the term assembly is used because the effect of the bill of materials is visible not only in sales but also elsewhere, for example in the intermediate manufactured products.

Assembly bills of materials enable you to define assemblies that will be sold directly. These could also be used in deliveries and stock management rather than just sold in isolation. For example if you deliver the cabinet in pieces for self-assembly, set the ARM100 BoM to type Assembly .

When a salesperson creates an order for an ARM100 product, OpenERP automatically changes the ARM100 from a set of components into an identifiable package for sending to a customer. Then it asks the storesperson to pack 2 PANLAT, 1 PANA100, 4 PROFIL, 3 ETA100. This is described as an ARM100 not just the individual delivered products.

Example: Large distributor

As an example of using these assemblies, take the case of a supermarket. In a supermarket, you can buy bottles of cola individually or in a pack of 6 bottles. The pack and the bottles are two different products and the barcodes used are also different.

But customers have the right to open a pack and extract some bottles to take them individually to the checkout. The supermarket can't track its stock in packs and bottles any more, but only individually in bottles.

So you can define a bill of materials for sale which defines a pack as an assembly of 6 bottles. Then when you've sold a pack, you can find a pack on the invoice or bill of sale but the associated stock operation will still be 6 bottles.

In the case of this assembly, this isn't a production order to transform the product. The transformation is done directly between the order and the set.

注解

Assemblies and Purchases

The use of assemblies for selling to customers has been described here, but this functionality works just as well for purchases from suppliers.

So in the example of a supermarket, you can buy cola in packs and the storesperson will see a number of bottles at goods in reception.

Configurable Bills of Materials

In OpenERP you can define several bills of materials for the same product. In fact you can have several manufacturing methods or several approved raw materials for a given product. You'll see in the following section that the manufacturing procedure (the routing) is attached to the Bill of Materials, so the choice of bill of materials implicitly includes the operations to make it.

Once several bills of materials have been defined for a particular product you need to have a system to enable OpenERP to select one of them for use. By default the bill of materials with the lowest sequence number is selected by the system.

To gain more control over the process during the sale or procurement, you can use properties. The menu Production Management ‣ Configuration ‣ Properties enables you to define properties, which can be defined arbitrarily to help you select a bill of materials when you have a choice of BoMs.

注解

属性

Properties is a concept that enables the selection of a method for manufacturing a product. Properties define a common language between salespeople and technical people, letting the salespeople to have an influence on the manufacture of the products using non-technical language and the choices decided on by the technicians who define Bills of Materials.

For example you can define the properties and the following groups:

属性

Property Group

Property

Warranty

3 years

Warranty

1 year

Method of Manufacture

Serial

Method of Manufacture

批次执行档

Once the bills of materials have been defined you could associate the corresponding properties to them. Then when the salesperson goes to encode a product line he can attach the properties there. If the product must be manufactured, OpenERP will automatically choose the bill of materials that matches the defined properties in the order most closely.

Note the properties are only visible in the Bills of Materials and Sales Management if you're working in the Extended View mode. If you can't see it on your screen add the group Useability / Extended View to your user.

/doc_static/5.0/_images/sale_line_property.png

Properties on a customer order line

Example: Manufacturing in a batch or on a production line

As an example, take the manufacture of the cabinet presented above. You can imagine that the company has two methods of manufacturing this cabinet:

  • Manually: staff assemble the cabinets one by one and cut the wood plank by plank. This approach is usually used to assembly prototypes. It gets you very rapid production, but at a high cost and only in small quantities.

  • On a production line: staff use machines that are capable of cutting wood by bandsaw. This method is used for production runs of at least 50 items because the lead times using this method are quite lengthy. The delay to the start of production is much longer, yet the cost per unit is much lower in this volume.

You define two bills of materials for the same cabinet. To distinguish between them, you will define to properties in the same group: manual assembly and production line assembly . On the quotation, the salesperson can set the method of manufacture he wants on each order line, depending on the quantities and the lead time requested by the customer.

注解

bills of materials and substitute products

In some software, you use the term substitute for this principle of configurable properties in a bill of materials.

By putting a bill of materials on its own line, you can also implement substitute products. You set the bill of materials to type Assembly to make the substitution transparent and to prevent OpenERP from proposing an intermediate production order.

生产制造

Once the bills of materials have been defined, OpenERP becomes capable of automatically deciding on the manufacturing route depending on the needs of the company.

生产订单可以由系统根据前面的章节中描述的一些标准自动产生:

  • 使用 Make to Order 规则,

  • Using the Order Point rules,

  • 使用生产计划.

/doc_static/5.0/_images/mrp_auto.png

Automatically proposing production orders

Clearly it's also possible to start production manually. To do this you can use the menu Manufacturing ‣ Production Orders ‣ New Production Order.

If you haven't installed the Just-In-Time planning module mrp_jit, you should start using OpenERP to schedule the Production Orders automatically using the various system rules. To do this use the menu Manufacturing ‣ Compute All Schedulers.

Workflow for complete production

To understand the usefulness and the functioning of the system you should test a complete workflow on the new database installed with the demonstration data. In the order you can see:

  • The creation of a customer order,

  • 中间产品的制造工作流程,

  • The manufacture of an ordered product,

  • 交付产品给客户,

  • Invoicing at the end of the month,

  • 可追溯性的售后服务.

小技巧

示范数据

To follow the workflow shown below exactly, you should keep the same quantities as in the example and start from a new database. Then you won't run into exceptions that would result from a lack of stock.

This more advanced case of handling problems in procurement, will be sorted out later in the chapter.

The customer order

Begin by encoding a customer order. To do this, use the menu Sales Management ‣ Sales Orders -> New Quotation. Enter the following information:

  • Customer : Agrolait,

  • Shipping Policy : Invoice from picklist (second tab),

  • Order Line :

    • Product : PC2 – Basic PC (assemble on demand),

    • Quantity (UoM) : 1,

    • Product UoM : PCE,

    • Procure method : Make To Order.

Once the quotation has been entered you can confirm it immediately by clicking the button Confirm Order at the bottom to the right. Keep note of the order reference because this follows all through the process. Usually, in a new database, this will be SO007 . At this stage you can look at the process linked to your order using the Process button above and to the right of the form.

/doc_static/5.0/_images/mrp_sale_process.png

Process for handling Sales Order SO007

通过菜单 Manufacturing ‣ Compute All Schedulers 来做需求计算.

在制品管理

To understand the implications of requirements calculation, you must know the configuration of the sold product. To do this, go to the form for product PC2 and click on the link Bill of Materials to the right. You get the scheme shown in Composition of product PC2 in the demonstration data which is the composition of the selected product.

/doc_static/5.0/_images/mrp_product_bom_tree.png

Composition of product PC2 in the demonstration data

Manufacturing the PC2 computer must be done in two steps:

1: Manufacture of the intermediate product: CPU_GEN

2: Manufacture of the finished product using that intermediate product: PC2

The manufacturing supervisor can then consult the product orders using the menu Manufacturing ‣ Production Orders ‣ Production Orders To Start. You then get a list of orders to start and the estimated start date to meet the ordered customer delivery date.

/doc_static/5.0/_images/mrp_production_list.png

List of production orders

You'll see the production order for CPU_GEN but not that for PC2 because that one depends on an intermediate product. Return to the production order for CPU_GEN and click below it. If there are several of them, select the one corresponding to your order using the reference that contains your order number (in this example SO007 ).

/doc_static/5.0/_images/mrp_production_form.png

The detail of a production order

The system shows you that you must manufacture product CPU_GEN using the components: MB1, CPU1, FAN, RAM. You can then confirm the production twice:

Start of production: consumption of raw materials,

End of production: manufacture of finished product.

At this stage, you should click to edit the line for the product MB1 to enter a lot number for it. The lot number is usually shown the parent chart, so you should just copy that over. To do that put the cursor in the field Production Lot and press <F1> to create a new lot. Set a lot reference, for example: MB1345678 . The system may then show you a warning because this lot is not in stock, but you can ignore this message.

The production order must be in the closed state as shown in the figure Production order after the different stages.

/doc_static/5.0/_images/mrp_production_form_end.png

Production order after the different stages

Manufacture of finished product

Having manufactured the intermediate product CPU_GEN, OpenERP then automatically proposes the manufacture of the computer PC2 using the order created earlier. So return to the menu for production orders to start Manufacturing ‣ Production Orders ‣ Production Orders to start.

You'll find computer PC2 which has been sold to the customer, as shown in the figure List of production orders.

/doc_static/5.0/_images/mrp_production_list_end.png

List of production orders

Just as for product CPU_GEN, confirm the production order between two dates: start of production and end of production.

The product sold to the customer has now been manufactured and the raw materials have been consumed and taken out of stock.

小技巧

Automatic Actions

使用按库存生产的材料,生产完成后将自动影响到下面几处, 更详细的介绍在后面章节介绍:

  • 增加库存,

  • 为装配人员自动生成操作,

  • 自动创建财务相关分录以及分析.

Delivery of product to the customer

When the products have been manufactured, the storesperson automatically finds the order in his list of items to do. To see the items waiting for delivery, use the menu Stock Management ‣ Outgoing Products ‣ Available Packing. You'll find lists of packing to be done, there, as shown in the figure List of packing operations to be done.

/doc_static/5.0/_images/mrp_packing_out.png

List of packing operations to be done

The packing orders are presented in priority order of despatch so the storesperson must begin with the orders at the top of the list. Confirm that your packing list has been created by looking for the customer name ( Agrolait ) or by its reference ( SO007 ). Click on it and then click the button Approve.

小技巧

Packing and Delivery

Depending on whether you work in the simplified or extended mode you may need a further step to make a delivery to your customer, so you'd have to carry out the two steps:

  • picking list,

  • delivery order.

Invoicing at delivery

Periodically the administrator or an accountant can send invoices based on the deliveries that have been carried out. To do that, you can use the menu Stock Management ‣ Outgoing Products ‣ Packing to Invoice ‣ Packing by Invoice Method. You then get a list of all the deliveries that have been made but haven't yet been invoiced.

So select some or all of the deliveries. Click on the action Create Invoice. OpenERP asks if you want to group the deliveries from the same partner into a single invoice or if you'd prefer to invoice for each delivery individually.

/doc_static/5.0/_images/mrp_picking_invoice_form.png

Invoicing of deliveries

Invoices are generated automatically in the Draft state by OpenERP. You can modify invoices before approving them finally.

/doc_static/5.0/_images/mrp_invoice_list.png

List of invoices generated by the system based on deliveries

Once you have reviewed the different invoices that were generated, you can confirm them one by one or all at once by using the available actions. Then print the invoices using the multiple print option and send them to your customers by post.

可追溯性

Now suppose that the customer phones you to tell you about a production fault in a delivered product. You can consult the traceability through the whole manufacturing chain using the serial number indicated on the product MB1. To look through the detailed history, use the menu Stock Management ‣ Traceability ‣ Production Lots.

Find the product corresponding to the product or lot number. Once it's been found you can use traceability as described in the section Management of lots and traceability in the Logistics and Stock Management chapter.

Production order in detail

To open a Production Order, use the menu Manufacturing ‣ Production Orders ‣ New Production Order. You get a blank form for entering a new production order as shown in the figure New production order.

/doc_static/5.0/_images/mrp_production_new.png

New production order

The production order follows the process given by the figure Process for handling a production order.

/doc_static/5.0/_images/mrp_production_processus.png

Process for handling a production order

The date fields, priority and reference, are automatically completed when the form is first opened. Enter the product that you want to produce, and the quantity required. The Product UOM by default is completed automatically by OpenERP when the product is first created.

You then have to set two locations:

The location from which the required raw materials should be found, and

The location for depositing the finished products.

For simplicity, put the Stock location in both places. The field Bill of Materials will automatically be completed by OpenERP when you click the button Compute Data. You can then overwrite it with another BoM to specify something else to use for this specific manufacture.

The tabs Planned Products and Work Orders are also completed automatically when you click Compute Data. You'll find the raw materials there that are required for the production and the operations needed by the assembly staff.

If you want to start production, click the button Confirm Production, and OpenERP then automatically completes the Moves fields in the Consumed Products and Finished Products fields. The information in the Consumed Products tab can be changed if:

  • you want to enter a serial number for raw materials,

  • you want to change the quantities consumed (lost during production).

For traceability you can set lot numbers on the raw materials used, or on the finished products. To do this click on one of the lines of the first or the third tab. Note the Production lot and Tracking lot numbers.

Once the order is confirmed, you should force the reservation of materials using the Force Reservation button. This means that you don't have to wait for the scheduler to assign and reserve the raw materials from your stock for this production run. This shortcuts the procurement process.

If you don't want to change the priorities, just leave the production order in this state and the scheduler will create a plan based on the priority and your planned date.

To start the production of products, click Start Production. The raw materials are then consumed automatically from stock, which means that the draft ( Waiting ) movements become Done .

Once the production is complete, click Production Finished. The finished products are then moved into stock.

排程

The requirements scheduler is the calculation engine which plans and prioritises production and purchasing automatically from the rules defined on these products. It's started once per day. You can also start it manually using the menu Manufacturing ‣ Compute All Schedulers. This uses all the relevant parameters defined in the products, the suppliers and the company to determine the priorities between the different production orders, deliveries and supplier purchases.

You can set the starting time by modifying the corresponding action in the menu Administration ‣ Configuration ‣ Scheduler ‣ Scheduled Actions. Modify the Run MRP Scheduler configuration document.

/doc_static/5.0/_images/stock_cron.png

Configuring the start time for calculating requirements

小技巧

Calculating requirements / scheduling

Scheduling only validates procurement confirmed but not started. These procurement reservations will themselves start production, tasks or purchases depending on the configuration of the requested product.

You take account of the priority of operations in starting reservations and procurement. The urgent requests, or those with a date in the past, or those with a date earlier than the others will be started first so that if there are not enough products in stock to satisfy all the requests, the most urgent will be produced first.